Mount Albert project
In late January 2020, following the burst in the two wastewater sludge pipelines buried in a tunnel deep under Mt Albert, Wellington Water engaged engineering firm Stantec to identify repair options and manage the project.
Brian Perry Civil were then engaged as the lead contractor to undertake the enabling works and to manage the other contractors working on site.
A long list of options was quickly whittled down to a shortlist of two options for relining the existing pipes.
From the shortlist SaniTube, from German Company, Amex Sanivar, was selected because it offered the best value for money, could be installed quickly and highly experienced New Zealand agent and installer Hadlee and Brunton was able to undertake the work.
Despite the additional challenge of the global pandemic both pipes were successfully relined by the end of May 2020, thanks to the multi-disciplinary team brought together to deliver this innovative repair.
Neighbourhood Challenge: Who Can Crack This One? ⛓️💥❔
What has a head but no brain?
Do you think you know the answer? Simply 'Like' this post if you know the answer and the big reveal will be posted in the comments at 2pm on the day!
Want to stop seeing these in your newsfeed?
Head here and hover on the Following button on the top right of the page (and it will show Unfollow) and then click it. If it is giving you the option to Follow, then you've successfully unfollowed the Riddles page.
Stamps wanted
I run a Stamp club at Tawa School to encourage children to collect stamps and learn about countries, history and more. Unfortunately new stamps aren't often seen these days as it's all electronic! If you have any stamps or old collections sitting around, let me know and I'll come and get them.
Loading…