Mount Albert project

The Team from Wellington Water

In late January 2020, following the burst in the two wastewater sludge pipelines buried in a tunnel deep under Mt Albert, Wellington Water engaged engineering firm Stantec to identify repair options and manage the project.
Brian Perry Civil were then engaged as the lead contractor to undertake the enabling works and to manage the other contractors working on site.

A long list of options was quickly whittled down to a shortlist of two options for relining the existing pipes.
From the shortlist SaniTube, from German Company, Amex Sanivar, was selected because it offered the best value for money, could be installed quickly and highly experienced New Zealand agent and installer Hadlee and Brunton was able to undertake the work.


Despite the additional challenge of the global pandemic both pipes were successfully relined by the end of May 2020, thanks to the multi-disciplinary team brought together to deliver this innovative repair.

More messages from your neighbours
2 days ago

Poll: Do you set New Year’s resolutions?

The Team from Neighbourly.co.nz

🎉 2026 is almost here!

We’re curious ... how do you welcome it?
Do you set resolutions, follow special traditions, or just go with the flow?

Image
Do you set New Year’s resolutions?
  • 10.4% Yes! New Year, New Me
    10.4% Complete
  • 20.1% Yes - but I rarely stick to them
    20.1% Complete
  • 69.5% Nah - not for me
    69.5% Complete
675 votes
3 hours ago

🎉The Riddler wants to hear from you 🫵

The Riddler from The Neighbourly Riddler

🧩 Got a riddle that can stump your Neighbourly community? Share your brain teasers with us and watch your neighbours scratch their heads 😕🤔❓

Send us your tricky puzzles!

Image
J
3 days ago

Books

Jeanette from Tawa

Where to dispose of your books

Image