End in sight for year-long roadworks on Christchurch's Colombo St
More than a year of roadworks on one of Christchurch's major streets is almost at an end.
The $4.4 million Christchurch City Council project is installing a new wastewater pipeline along the middle of Colombo St between the roundabout at Dyers Pass Rd and Fisher Ave.
Construction work started on June 5, 2018, and was expected to take 12 months, but has ran slightly over schedule. It will be completed on Wednesday, though some ,more minor work will be done in July.
Today’s Mind-Bender is the Last of the Year! Can You Guess It Before Everyone Else? 🌟🎁🌲
I dance in the sky with green and gold, a spectacle few are lucky to behold; I’m best seen in the south, a celestial sight—what am I, lighting up the New Zealand night?
Do you think you know the answer? Simply 'Like' this post and we'll post the answer in the comments below at 2pm on the day!
Want to stop seeing these in your newsfeed? No worries! Simply head here and click once on the Following button.
No gift? No stress
Let the Christmas elves at Mags4gifts.co.nz handle your last-minute shopping. For a limited time, gift a subscription with up to 40% off best-sellers like TV Guide, NZ House & Garden, and NZ Gardener. It’s the perfect Christmas present, sorted in minutes (and no one needs to know it was a last-minute surprise)!
Loading…