Kiwi Rail greenlights Hokitika flood protection

Nicole Mathewson Reporter from The Press

The next stage in a $7.5 million flood protection scheme for Hokitika - now delayed by 10 months - should get under way soon.

But the West Coast Regional Council will need to beat the all important West Coast whitebaiting season if it is to complete a new floodwall along Hokitika's Gibson Quay, before the season starts on September 1.

The new flood work, from Westland Milk Products factory down to the Hokitika Bridge, is dubbed '1b' in the scheme.

It will link to the first stage completed behind the factory late last winter.
To date council has spent $2.3million of the total current budget of $7,505,226.

In the past 10 months council consultants have been working with Kiwi Rail to gain affected party consent for the 1b stage, given the rail corridor to Westland Milk Products is affected.

The council's Infrastructure Reference Group programme manager, Scott Hoare, said they finally had a green light.

"I have some really good news: we have written approval from KiwiRail," he said.

This earned a "wohoo" from Infrastructure Governance Committee chairperson Frank Dooley.

"Well done," he said.

Hoare said they had been negotiating with the State rail operator since last August.

The matter of extending a small drain in conjunction with the district council was all that had to be covered off now for the final sign-off.

Hoare said the appointed contractor had previously been stood down due to the delay so getting them to remobilise immediately was being negotiated.

The biggest challenge for that was "the start of whitebaiting".

This would be crucial to give an adequate window for the work, Hoare said.

Meanwhile, preparatory work for the third stage, the section to protect the Hokitika town centre, was progressing as well.

Dooley said it was good to read that Kiwi Rail had finally given its blessing.

Hoare said KiwiRail gave verbal advice on April 24 its queries were now resolved.

He subsequently received draft conditions from the rail operator on May 24.

However, the regional council had now requested seepage modelling for the new build, plus closed circuit television of the existing Westland District Council storm water pipes in the area.

Image
More messages from your neighbours
3 days ago

Poll: Do you set New Year’s resolutions?

The Team from Neighbourly.co.nz

🎉 2026 is almost here!

We’re curious ... how do you welcome it?
Do you set resolutions, follow special traditions, or just go with the flow?

Image
Do you set New Year’s resolutions?
  • 10.4% Yes! New Year, New Me
    10.4% Complete
  • 19.9% Yes - but I rarely stick to them
    19.9% Complete
  • 69.6% Nah - not for me
    69.6% Complete
787 votes
15 days ago

Scam Alert: Fake information regarding December Bonuses from MSD

The Team from Neighbourly.co.nz

The Ministry of Social Development is reporting that fake information is circulating about new ‘December bonuses’ or ‘benefit increases’

If you get suspicious communication, please contact Netsafe.

Image
19 hours ago

🎉The Riddler wants to hear from you 🫵

The Riddler from The Neighbourly Riddler

🧩 Got a riddle that can stump your Neighbourly community? Share your brain teasers with us and watch your neighbours scratch their heads 😕🤔❓

Send us your tricky puzzles!

Image