In late January 2020, following the burst in the two wastewater sludge pipelines buried in a tunnel deep under Mt Albert, Wellington Water engaged engineering firm Stantec to identify repair options and manage the project.
Brian Perry Civil were then engaged as the lead contractor to undertake the enabling works and to manage the other contractors working on site.

A long list of options was quickly whittled down to a shortlist of two options for relining the existing pipes.
From the shortlist SaniTube, from German Company, Amex Sanivar, was selected because it offered the best value for money, could be installed quickly and highly experienced New Zealand agent and installer Hadlee and Brunton was able to undertake the work.


Despite the additional challenge of the global pandemic both pipes were successfully relined by the end of May 2020, thanks to the multi-disciplinary team brought together to deliver this innovative repair.

More messages from your neighbours
12 hours ago

Get painting with Resene plant-based paints!

Resene

Plant-based paints are made just like normal paint but everything in the tin comes from plants and minerals.

Plus they’re Eco Choice approved with low odour and easy water clean-up, so you can paint or stain your place with ease.

Available from Resene ColorShops.
Find out more

Image
1 day ago

Tips for better sleep from Beds4U!

Beds 4 U Masterton

Hi Neighbours,

Tired of counting sheep? We've got a better way! Check out our latest tips for a sleep experience that'll have you waking up refreshed and ready to conquer the day. #sleeptip #sleep

Image
1 day ago

Potted colour

The Team from Resene ColorShop Masterton

Express yourself with this artistic dip-dye paint effect using Resene paints. Find out how to create your own with these easy step by step instructions.

Image