Northland land slips map
Responding to flooding and severe weather over the last year has been expensive. Northland’s local road network suffered approximately $89m worth of damage from at least 10 different significant weather events since July 2022.
In Whangārei, we've successfully restored the majority of roads and we're now focusing on the rehabilitation of 28 sites, with an estimated cost of around $10 million. These repairs are expected to take 2 - 3 years to complete.
View information about the roading recovery and repair process, including the recovery phases.
Road recovery and repair process
This map provides repair details for slips impacting roads maintained by Northland’s three District Councils and caused by the weather events. It does do not show historic (pre-existing) slips that occurred prior to July 2022.
Loading map, please wait...
Map: Red pins are for complex, longer term repairs costing over $100,000. Blue pins are for less severe repairs costing under $100,000. Green pins are for repairs completed since November 2023.
You can zoom in or out to find roads or slips you are interested in. Press the 'Reset Map' button to zoom out.
Click on a pin to display information about a specific slip.
Repair schedule
Below is an overview of the land slip locations in the Whangārei District, their repair status and estimated timing for construction.
Whangārei District land slips schedule
RP stands for 'route position'. This is the measurement, in metres, from the start of the road. House numbers begin at the start of the road (e.g. 1, 2, 3 etc.).
This list was last updated on 27 March 2024.
Location |
Repair status |
Estimated construction timing |
Bay View Road - 359 RP to 389 RP (length 30 metres) |
Investigation |
Q3 - Winter 2024
|
Clemo Road - 132 RP to 145 RP (length 13 metres) |
Construction |
Q2 - Autumn 2024 |
Crows Nest Road - 6372 RP to 6422 RP (length 50 metres) |
Planning |
To be confirmed (post 2024) |
Finlayson Brook Road - 5221 RP to 5251 RP (length 30 metres) |
Planning |
Q2 - Autumn 2024 |
Finlayson Brook Road - 3012 RP to 3042 RP (length 30 metres) |
Planning |
Q2 - Autumn 2024 |
Finlayson Brook Road - 7452 RP to 7522 RP (length 70 metres) |
Planning |
To be confirmed (post 2024) |
Finlayson Brook Road - 7529 RP to 7644 RP (length 115 metres) |
Planning |
To be confirmed (post 2024) |
Finlayson Brook Road - 7320 RP to 7360 RP (length 40 metres) |
Planning |
To be confirmed (post 2024) |
Finlayson Brook Road - 7650 RP to 7680 RP (length 30 metres) |
Planning |
To be confirmed (post 2024) |
Kaiikanui Road - 10153 RP to 10188 RP (length 35 metres) |
Design |
Q3 - Winter 2024 |
Karaka Road - 4990 RP to 5070 RP (length 80 metres) |
Planning |
Q4 - Spring 2024 |
Kauri Mountain Road - 1677 RP to 1757 RP (length 80 metres) |
Planning |
Q4 - Spring 2024 |
Maungakaramea Road - 8312 RP to 8342 RP (length 30 metres) |
Design |
Q2 - Autumn 2024 |
Memorial Drive - 2247 RP to 2259 RP (length 12 metres) |
Investigation |
To be confirmed |
Memorial Drive - 2535 RP to 2550 RP (length 15 metres) |
Investigation |
To be confirmed |
Memorial Drive - 2599 RP to 2620 RP (length 20 metres) |
Investigation |
To be confirmed |
Millbrook Road - 10705 RP to 10755 RP (length 50 metres) |
Construction |
Q2 - Autumn 2024 |
Mititai Road - 6887 RP to 6935 RP (length 117 metres) |
Construction |
Q2 - Autumn 2024 |
Ngunguru Road North - 13759 RP to 13784 RP (length 25 metres) |
Design |
Q2 - Autumn 2024 |
Ody Road - 350 RP to 493 RP (length 77 metres) |
Construction |
Q2 - Autumn 2024 |
Parua Cemetery Road - 134 RP to 134 RP (length 0 metres) |
Construction |
Q2 - Autumn 2024 |
Pipiwai Road North - 24500 RP to 24530 RP (length 30 metres) |
Planning |
Q4 - Spring 2024 |
Shoemaker Road - 4954 RP to 4987 RP (length 33 metres) |
Planning |
Q3 - Winter 2024 |
Snooks Road - 7240 RP to 7246 RP (length 30 metres) |
Planning |
Q4 - Spring 2024 |
Waipu Gorge Road - 3741 RP to 3761 RP (length 20 metres) |
Planning |
Q3 - Winter 2024 |
Whangarei Heads Road North - 20673 RP to 20813 RP (length 123 metres) |
Planning |
Q4 - Spring 2024 |
Whangarei Heads Road North - 21287 RP to 21336 RP (length 49 metres) |
Planning |
To be confirmed |
Whangarei Heads Road North - 23904 RP to 23945 RP (length 39 metres) |
Planning |
To be confirmed |
Estimated construction timing
- Q1 (summer): January – March 2024
- Q2 (autumn): April – June 2024
- Q3 (winter): July – September 2024
- Q4 (spring): October – December 2024.